LOCKED UP!

Today was a day we've long awaited. Today the last of the lower floor windows arrived. Two still have temporary plywood as they await permanent glassbut all the holes are at long last filled. The good news is that as the Harold's contracting crew fastened the last window in place we have achieved official lockup.

The last batch of windows included the big round sets, front and rear as well as the front door set - fifteen windows and one door in all. They all look perfect and fit perfectly too. It took a while for Harold's crew to carefully align the many panes - up to six in each set. 

installing windows.png
doors locked.png

The Element Spray Foam crew has three or four more days to go before that big job is done. Then we can start in on the inside work required to finish the house. A good chunk of the day was also spent onsite with Roy from the cabinet shop. We surveyed each location cabinets are needed and in the next few days we will have our first draft of the cabinet plan. 

Things are coming together!

-grampa dan